SCADA Upgrades

Project Scope

The project focuses on improving the instrumentation and communication devices in WTP and a few of our lift stations to efficiently monitor and analyze our system. Better devices will improve reliability and data capture.

Funding Source MSP Funding
Project Start July 2021
Project End December 2022

Project Updates

Date Status Details
February 8th 2022 Progressing Project is slowly progressing. Material for PLC upgrade is still back-ordered with no realistic timeline on delivery
March 8th, 2022 Progressing Project is slowly progressing. Material for PLC upgrade is still back-ordered with no realistic timeline on delivery.